Saudi Arabia's Desert Ski Resort Trojena Delayed Until After 2030 as NEOM Shifts Priorities

Saudi Arabia's Desert Ski Resort Trojena Delayed Until After 2030 as NEOM Shifts Priorities

In this story

Trojena

Resort in Tabuk, Saudi Arabia

Nearest airport
King Hussein International Airport (AQJ) · 2h 00m
Trojena guide

Saudi Arabia's plan to build the Middle East's first outdoor ski resort has slipped well beyond its original timeline, with multiple major contracts canceled in recent weeks and the kingdom's giant NEOM development redirecting money toward other priorities.

Trojena, the mountain resort project tucked into the Tabuk region's Sarawat range roughly 50 kilometers from the Gulf of Aqaba, was unveiled in 2022 with a planned 2026 completion date and ambitions to host the 2029 Asian Winter Games. When it was announced in 2022, the project was originally set to be completed by 2027, and a 2023 internal review found that costs had ballooned by more than $10 billion, pushing the project's projected returns below acceptable thresholds, with an internal audit later finding signs that financial figures had been manipulated to mask the overruns.

Follow the story
What's next for Trojena?

Get Trojena news by email.

Follow Trojena

The signs of an impending collapse at Trojena had been mounting throughout the first half of 2026:

  • Engineering Halts: Italian engineering giant Webuild saw its $4.7 billion contract to construct Trojena’s signature artificial freshwater lake and three dams abruptly terminated.

  • Steel & Infrastructure Halts: Structural steel contracts with Malaysia’s Eversendai and critical tunneling contracts with South Korea’s Hyundai Engineering & Construction were similarly axed.

  • Transit Cancellations: A high-speed railway contract intended to link the different NEOM sectors was canceled.

Furthermore, Trojena's premier international spotlight was quietly extinguished earlier this year. Due to mounting technical challenges and construction delays, the Olympic Council of Asia officially relocated the 2029 Asian Winter Games—an event Trojena was uniquely awarded as the first desert destination in history—to Almaty, Kazakhstan, leveraging their existing world-class winter sports venues.

From Utopia to Industrial Pragmatism

The pivot marks a major psychological shift for Saudi Arabia’s Vision 2030 pipeline. The Kingdom has already poured roughly $64 billion into NEOM, yet virtually all of the development remains an unfinished expanse of bare desert. The single notable exception is Oxagon, where an $8.4 billion green hydrogen facility is nearing completion and the regional port is generating active trade.

Now, NEOM is abandoning its most eccentric architectural dreams to focus on what is practical and revenue-generating. The flagship linear city, The Line, is currently undergoing extensive cost-cutting redesigns. Population targets for the entire NEOM territory have plummeted from an initial 1.5 million residents down to just 100,000 by the turn of the decade.

That timeline has now collapsed further. In 2026, organizers moved the 2029 Asian Winter Games from Trojena to Almaty, Kazakhstan, and canceled several key construction contracts tied to the resort, including work on its central dam system and structural steel supply. Earlier in the year, the Olympic Council of Asia and the Saudi Arabian Olympic Committee had already agreed to postpone the kingdom's hosting of the Winter Games because of construction delays at the site.

The most significant blow came in late March, when Malaysia's Eversendai Corporation announced its steel fabrication and construction contract for Trojena had been terminated, followed a day later by Italian construction giant Webuild confirming its multibillion-dollar dam and freshwater lake contract had also been axed. Eversendai had described its Trojena work as its "largest and most challenging project" in its 2024 annual report, with a $510 million order book outside of the Trojena work and a $4.6 billion tender book.

Together, the canceled work represents a substantial financial hit. The three terminated contracts total roughly $6 billion: Webuild's $4.7 billion dam and lake agreement, a roughly $1 billion Hyundai tunnel contract, and Eversendai's structural steel deal, the value of which was not disclosed. Eversendai has said it is preparing claims for termination and demobilization costs that it expects NEOM to cover. The dam project alone was far from finished — Webuild said the work was about 30% complete, with roughly $3.2 billion worth of construction still outstanding, and more than 5,000 employees assigned to the three dams. Those dams were meant to feed a 2.8-kilometer artificial lake at the resort's center, used for snowmaking, hydropower and water sports.

NEOM has stopped short of declaring the project dead. The company says it has not formally canceled Trojena as a whole and remains committed to completing the lake and resort facilities under revised plans, potentially shifting to alternative delivery models such as public-private partnerships. Even so, how, if, and when the project will move forward is currently uncertain.

The setbacks at Trojena mirror a broader retrenchment across NEOM. Saudi authorities have sharply scaled back funding and ambitions for the flagship project as lower oil revenues, cost overruns and delays force a rethink of Vision 2030 spending, with overall Public Investment Fund construction contracts falling from about $7 billion in 2024 to roughly $30 billion in 2025 — note that figure reflects a redirection of capital rather than simple growth, as money shifts away from giga-projects like NEOM toward infrastructure for Riyadh's Expo 2030 and the 2034 FIFA World Cup. NEOM's broader restructuring has reportedly split the entity into at least five separate units, with pieces transferred to Aramco, the Ministry of Sport and Red Sea Global as the Public Investment Fund pivots toward artificial intelligence, mining and logistics.

The scale-back extends to NEOM's most famous component, The Line. Its population target for 2030 has reportedly been cut from 1.5 million residents to fewer than 300,000, and the original 170-kilometer linear city vision has been pushed onto a multi-decade timeline, with 2045 now floated as a possible completion date.

For now, Trojena's fate sits in limbo. Neither Saudi officials nor NEOM representatives have issued a public statement clarifying the project's overall status, and industry observers are watching to see whether the kingdom will formally revise its plans or continue quietly absorbing setbacks at what was once billed as a centerpiece of Crown Prince Mohammed bin Salman's tourism diversification strategy.