New central support constructed on the Säntis

New central support constructed on the Säntis

After just three weeks of assembly, the new intermediate support tower for the future Säntis cable car already rises 43 meters into the air. With its striking design and the new alpine intermediate exit, it will not only be a central element of the cable car technology, but will also continue to provide an intermediate stop along the route.

Dismantling of the existing supports

At the beginning of June, the dismantling work on the existing supports 1 and 2 began. These were dismantled within approximately two weeks.

The former support pillar 1 continues to serve an important function for the upcoming installation of the suspension cables. The first level of the steel structure remains in place and serves as a temporary support structure for hoisting the cables. Pulleys will be used to guide the future suspension cables across the terrain and keep them safely away from the rock face during installation.

The existing support 2 was completely dismantled down to its foundations to make room for the construction of the new intermediate support. All components of the dismantled support will later be transported sustainably to the valley using the new cable car.

Thanks to favorable weather conditions, the work, led by Thierry Burtscher of Garaventa AG, proceeded according to schedule. An average of six fitters were working on the support tower construction site simultaneously. The occasionally strong winds posed a particular challenge, as numerous assembly tasks had to be carried out at heights of up to 45 meters.

“On a construction site at this altitude, wind and weather can change the workflow in a very short time. It is all the more gratifying that the work has so far proceeded largely according to schedule and without accidents,” explains Thierry Burtscher.

Reduction in the number of supports

Unlike the existing cable car, the new Säntis cable car will operate with only one intermediate support tower. Extensive analyses and cable calculations confirmed that this solution is feasible despite the challenging topography, although it does require some adjustments to the cable car system.

The new intermediate support is significantly wider and more robust than the previous support 2. At the same time, stronger suspension cables are used to safely absorb and transfer the approximately twice as high tensile forces. Additional anchors increase the stability of the entire support.

“The new intermediate support must bear significantly higher loads than the previous support 2. Accordingly, the foundations, their anchorages and the steel structure were designed to meet the requirements of the new railway,” explains Thierry Burtscher.

The decision to use a single intermediate support was also made for landscape considerations. Replacing the existing support 1 would have required extensive avalanche protection structures and significant alterations to the landscape. The chosen solution reduces the structural impact while simultaneously ensuring safe railway operation.

Construction of the new intermediate support

The foundations for the new intermediate support were constructed in the summer of 2025 by the Säntis consortium (Slongo AG, Herisau, and E. Weber AG, Wattwil). The anchors for the new foundations were installed by Gasser Felstechnik AG. A total of approximately 420 m³ of concrete was used for the four foundation blocks. In addition, 16 anchors driven diagonally into the rock provide permanent stability to the structure in the karst terrain. Depending on their location, the rock anchors are designed to withstand tensile forces of up to 100 tons.

More efficient assembly thanks to the construction crane

A 55-meter-high construction crane from Liebherr AG was used to install the new intermediate support. Due to the rocky terrain and the lack of level ground, this solution represented the most efficient method for erecting the steel structure.

“Compared to alternative lifting devices or helicopter transport, the construction crane allowed us to reduce assembly times and optimize workflows,” adds Thierry Burtscher.

After the first steel elements were erected, the structure was surveyed by a surveyor and aligned with the railway axis. Only after this check could the further construction of the support continue from the second floor upwards. Precise positioning is crucial to ensure the correct cable routing is maintained.

Within just three weeks, the steel structure, the platform, and the folding platform were completely erected. The installation of the hydraulically operated folding platform ensures intermediate boarding and disembarking on the new cable car.

The platform was pre-assembled on the ground and then lifted into place as a complete unit using a construction crane. Garaventa AG will handle all the necessary connections on-site for the hydraulic system and ensure its proper functioning. A total of approximately 171 steps now lead up to the platform. This new alpine-style intermediate exit also offers breathtaking views across eastern Switzerland to Lake Zurich and the entire Alpine chain.

Outlook on upcoming work

The erection of the intermediate support marks an important milestone. Further installations will follow, along with the concreting of the support bases and subsequent various inspections.

The dismantling of the construction crane is already scheduled for August 5th, weather permitting. An AS332 Super Puma C1 helicopter from Heliswiss will again be used to airlift the individual crane components from the challenging terrain.

https://saentisbahn.ch/