Macugnaga: What's the Future for the Ski Lifts?
In this story
Macugnaga
Resort in Piedmont, Italy
- Village height
- 1,317 m
- Top lift
- 2,877 m
- Pistes
- 10 km
- Lifts
- 5
- Nearest airport
- Milan Malpensa International Airport (MXP) · 1h 44m
With summer in full swing, questions still linger over whether Macugnaga's ski lifts will reopen after sitting idle through the entire last winter season. The Monte Moro cable car remains under partial seizure following a December 30 accident, while the Belvedere chairlifts stay closed pending sign-off on a landslide and avalanche safety plan tied to a recent general overhaul.
Both the municipality and the lift operator have pushed back on reports from the newspaper La Stampa suggesting the closures could become permanent, insisting instead that they are waiting on guidance from Ansfisa, the national authority responsible for ski lift safety oversight and operating permits.
Municipality Presses for Clarity from Ansfisa
In a statement responding to the permanent-closure reports, the municipality of Macugnaga — which owns the lifts — said it has renewed its request to Ansfisa for clarity on the procedures and timeline needed to secure the authorizations that operating permits depend on.
The statement noted that in recent weeks the municipality has worked to resolve outstanding questions about the Pecetto-Belvedere chairlift's compliance with landslide and avalanche risk regulations, and said it has found cooperation from both national and regional institutions along the way. Officials are now pushing for Ansfisa to move past the delays and deliver a clear answer, with a meeting between the municipality and Ansfisa scheduled for next week in Rome.
The lift management company, Macugnaga Trasporti e Servizi, confirmed the situation. Although it doesn't own the lifts, the company said it has spent its own money hiring consultants to help the municipality work through the administrative hurdles involved.
Avalanche Protection and a Complicated Permit History
In parallel, the municipal administration has moved up installation of new Gazex avalanche-mitigation devices meant to protect the ski area — upgrades intended to help bring the facility into regulatory compliance.
But according to La Stampa, Ansfisa is weighing additional questions about the legitimacy of a second extension the chairlifts received to keep operating. The lifts were first granted an extension running from 2019 to 2024 so a planned gondola replacement could move forward. A further extension came in 2024, on the condition that the chairlifts undergo a general overhaul — work the municipality completed in the months before last winter at a cost of roughly €500,000, which was intended to keep the lifts running through February 2029.
New Mayor: A Gondola, Not a New Chairlift, Is the Real Fix
Speaking on the sidelines of Friday's city council meeting, newly elected Mayor Stefano Candiani said that since taking office he has done everything within the municipality's authority, including opening contact with the Piedmont Region and Ansfisa. He was careful to note, however, that the legal and judicial dimensions of the case fall outside the municipality's control, and stressed the need for answers soon.
Candiani said that even if the chairlifts do reopen, it would only be a stopgap, given that their authorization runs out in 2029 regardless. He told La Stampa that building a new gondola lift is, in his view, the only real long-term path forward, even though it will take years to complete. He added that engineers have advised against installing a cheaper replacement chairlift, arguing it wouldn't be appropriate given the area's hydrogeological and snow conditions — a standard chairlift, built on lower, more numerous pylons than a gondola, would offer less protection against avalanches.
Monte Moro Cable Car Faces Its Own Delays
The chairlift dispute comes on top of ongoing problems with the Monte Moro cable car, out of service since December 30 after a braking system malfunction caused it to strike the arrival station. The Verbania public prosecutor's office has released the cable car's mechanical components but not yet its electronic components, which is holding up the start of repair work needed before the lift can reopen to the public.
Higher up the mountain, further decisions are expected on the San Pietro ski lift, whose request for an operating extension was denied by Ansfisa last December along with the Belvedere chairlifts.
Even a resolution for Monte Moro would only buy time. The cable car's first section is due for a major overhaul or replacement by 2029 to keep running, and the Ruppenstein chairlift is slated for significant maintenance work around the same time. In 2032, the second section of the Bill-Monte Moro cable car — currently under partial seizure — will require similar work of its own.