The US Forest Service has issued a decision notice and finding of no significant impact environmental assessment on purgatory resort gelandé chairlift, terrain project, and boundary adjustment. It says in summary:
This Decision Notice documents my decision and rationale for approving the proposed projects on the Columbine Ranger District, San Juan National Forest (SJNF). The Project Area is located within Purgatory Resort (Purgatory), La Plata County, Colorado. My decision is based on and supported by the March 2018 Purgatory Resort Gelandé Chairlift, Terrain Projects, and Boundary Adjustment Environmental Assessment (EA).
Purgatory operates under a special use permit (SUP) administered by the SJNF’s Columbine Ranger District. The 2013 San Juan National Forest Land and Resource Management Plan (Forest Plan) provides general standards and guidelines for the operation of Purgatory regarding its activities and operations on National Forest System (NFS) lands. The SUP and associated summer and winter operating plans, as well as other resource management documents, provide more specific guidance for annual winter and summer ski area operations and projects. The approved projects are variations of projects analyzed in the 2008 Durango Mountain Resort Improvement Plan Final Environmental Impact Statement (2008 FEIS) and approved in the Record of Decision (2008 ROD) that followed.
Purpose and Need for Action
The purpose of the Proposed Action is to allow Purgatory to meet the increasing demand for expert-level terrain on the front side of the mountain and to reduce skier traffic in the congested Demon ski trail area by constructing a chairlift that provides direct access to separate terrain. There is a need for the Proposed Action to improve access to available terrain from a separate base area portal, which will improve skier circulation across the mountain. The need for the Forest Plan amendment is to keep the adjusted ski area permit boundary within Management Area 8.
Decision and Reasons for the Decision
After thoroughly considering the Purpose and Need for Action, issues, range of alternatives, and analyses presented in the EA, as well as public comments that were received, I am approving the Proposed Action with the inclusion of all design criteria identified in Table 1 of the EA and included in Appendix A of this document. The Selected Alternative will include construction of a new chairlift, associated utilities, and ski trails to be served by the proposed chairlift. The attached figure identifies components of the Selected Alternative.
The Selected Alternative, along with my decision to require Design Criteria, meets all applicable laws, regulations, and policies. With the application of Design Criteria, the project will not result in any unacceptable effects to NFS lands. Failure to comply with the required Design Criteria will constitute a breach of the project approval and could suspend construction and/or operations on the facilities approvedby this decision.
Decision Notice and Finding of No Significant Impact
Gelandé Chairlift, Terrain Project, and Boundary Adjustment | Environmental Assessment
Purgatory is required to prepare and submit several documents for Forest Service approval prior to beginning any approved construction activities. For example:
• Project construction and grading plans
• Engineered plans
• Pre-construction erosion control/drainage management plans
• Noxious weeds annual monitoring report (for three years post-construction)
• Post-construction revegetation and rehabilitation plans
Selected Alternative Description
The approved Gelandé chairlift realignment will result in a chairlift that is approximately 300 feet shorter than the previously approved chairlift (4,200 feet in length total) and is located 250 feet (bottom terminal) to 900 feet (top terminal) south of the previously approved chairlift. The 2008 ROD approved approximately 16.9 acres of disturbance total (12.4 acres vegetation clearing only, 4 acres vegetation clearing and grading, and 0.5 acre grading only) to widen the Styx ski trail and install the chairlift. This previously approved clearing acreage will be spatially reassigned to create a new return ski trail from top to bottom of the Gelandé chairlift (located just north and west of the approved chairlift) as well as a new connecting ski trail from the lower Styx ski trail to the bottom, both terminating at the approved Gelandé chairlift bottom terminal. Because the clearing associated with the widening of the Styx trail will no longer be necessary, the realignment and trails will not constitute any additional disturbance from what was previously approved on public lands. The bottom terminal will be located on private land, and the top terminal will be located on NFS lands, requiring a similar amount of disturbance as previously approved.
An access road approximately 1,000 feet in length will be constructed from the existing top terminal of the Needles chairlift to the top terminal of the approved Gelandé chairlift realignment. The Selected Alternative includes 16.1 acres of disturbance total (15.4 acres of vegetation clearing only, 0.4 acre of vegetation clearing and grading, and 0.3 acre of grading only).
At the time of this decision, the selection of the exact type of chairlift that will be installed is unknown. Depending on the lift design, access to lift towers for construction and the top and bottom terminals access routes will need to be approved by the Forest Service prior to construction.
More: https://www.fs.usda.gov/nfs/11558/www/nepa/107847_FSPLT3_4311148.pdf