Alpe Tognola Set for €16 Million Overhaul: New Six-Seater Chairlift and Redesigned Slopes
In this story
Partners mentioned
San Martino di Castrozza
Resort in Trentino, Italy
- Village height
- 1,474 m
- Top lift
- 2,618 m
- Pistes
- 43 km
- Lifts
- 22
- Nearest airport
- Bolzano Airport (BZO) · 1h 26m
Funivie Seggiovie San Martino Srl has unveiled one of the most ambitious modernization plans in its history, a project worth more than €16 million that will transform the Scandola-Conca side of the Tognola ski area, part of the San Martino di Castrozza-Passo Rolle resort.
The plan centers on upgrading the skiing experience, boosting the efficiency of snow production, and cutting the footprint of mountain infrastructure on the surrounding landscape.
Get San Martino di Castrozza news by email.
Follow San Martino di Castrozza"An ambitious, concrete, visionary investment. A project that combines innovation, technology, sustainability, and landscaping within the Paneveggio Pale di San Martino Natural Park," said Valeria Ghezzi, CEO of Funivie Seggiovie San Martino and president of ANEF, the Italian national association of cableway operators.
One Lift Replaces Two
At the heart of the project is the replacement of the existing fixed-grip three-seater Conca and Scandola chairlifts with a single automatic-detachment six-seater system.
The new lift will run the full length of the slope — a 1,324-meter line climbing 308 meters in elevation — with a top speed of 5 meters per second and a ride time of roughly four minutes and 27 seconds. Hourly capacity will reach 2,650 skiers, an upgrade intended to cut queues and spread traffic more evenly across the mountain.
The consolidation will also shrink the resort's physical footprint significantly: two lift systems will become one, four stations will become two, and the 33 support towers currently in place will be reduced to just 10.
Slopes Redeveloped, New Connections Added
The work extends well beyond the lifts themselves. The Scandola slope will be completely reshaped and fitted with an upgraded snowmaking system, while the Conca slope will see its route redesigned, its snowmaking modernized, and its length extended by more than 700 meters — creating a direct link between the two runs.
Resort operators expect the new layout to ease pressure on the Rododendro slope, currently one of the busiest routes in the ski area. The project also adds a variant toward the snowpark and a new roughly 500-meter connector, the Larici slope, linking the final stretch of the Cima Tognola run with Scandola.
A New Home for Freestyle Skiing
The resort's freestyle and terrain-park offerings are also getting an overhaul. The current boardercross course will be upgraded and rebranded as the Dolomia Funslope, complete with its own dedicated snowmaking system.
The San Martino Snowpark will be relocated and redesigned from the ground up, with features tailored to riders of different skill levels — part of a broader push to build a more modern, functional freestyle hub integrated with the rest of the resort.
Thirty New Snow Guns
A substantial share of the investment will go toward snowmaking infrastructure. Plans include a new water supply line running from Fratazza to the reservoir, modernized pump rooms, and the installation of 30 new snow guns, aimed at improving system efficiency, reducing waste, and maintaining reliable coverage even in seasons with shorter cold spells.
A New Skibar at the Valley Station
The base station of the new chairlift will be integrated with a rebuilt Scandola Skibar, featuring a large south-facing terrace. The venue is designed to become a new gathering point on the mountain, capitalizing on one of Alpe Tognola's sunniest and most scenic spots.
Environmental Safeguards
According to the company, construction will avoid the area's wetlands and peat bogs. Consolidating the two chairlifts into one system is also expected to reduce land use by cutting the number of stations and support towers required.
Timeline
Work is scheduled to begin in 2026, with some secondary interventions potentially extending into 2027. The project marks a new chapter for Alpe Tognola's Scandola-Conca side, aimed at making the area more modern, efficient, and accessible for skiers.