After Seven Years, Argentera’s Chairlift Is Close to Turning Again. Is It Close Enough?

After Seven Years, Argentera’s Chairlift Is Close to Turning Again. Is It Close Enough?

In this story

The drive station of the Pian del Beu chairlift lit up. Mayor Monica Ciaburro said the power was switched back on after a buried medium-voltage cable was found to have melted. After years of silence in the upper Valle Stura, it was a small and visible sign of progress.

It is not yet a reopening. Neveitalia reports that skiing could return this winter, but the conditional is essential given the technical and bureaucratic details still to be finished. The municipality, which owns the facilities, is aiming for a test and approval of the lift by December.

A resort on a long hiatus

The area has the chairlift plus three surface lifts, with slopes between 1,630 and 2,480 metres, mostly facing north-east. It is known for powder and off-piste skiing and also suits families and beginners. The chairlift is a fixed-grip double built by Leitner in 1977, 1,855 metres long, with a listed capacity of 853 passengers an hour.

The lift has been idle since 2019, and the trouble goes back further. Local press reported at the time that the municipality’s financial collapse and roughly a million euros of past debts kept it from joining a regional funding call, and that firms were demanding payment up front for maintenance work. A later report said the resort had then spent two years closed, with three tenders failing, before a new operator, Valle Bianca srl, was given a direct three-year contract. That contract is at the heart of today’s dispute.

What has been done

The current work goes well beyond routine upkeep. Besides structural checks and an overhaul of the moving parts, the upper station has been completely rebuilt. In June the mayor described two worksites: one in the manufacturer’s workshops, one on the mountain, which only became accessible after winter. That update targeted completion by 31 July. The date has since slipped.

Among the setbacks, the contractor’s schedule was disrupted by the electrical fault. Locating it needed a specialist firm and cost about €6,000. Dozens of metres of cable were replaced. A safety review added more. At the end of August the municipality issued an emergency order after the works supervisor flagged safety concerns. A forestry expert found widespread instability among trees near the line, and many were felled. The felling cost the municipality nothing, since the crews kept the timber as payment.

A retaining wall is still pending. The landscape commission has approved the design changes, and the Soprintendenza now has 60 days to respond. To absorb further delays, the municipality will grant another technical extension to the works, to roughly late November or early December.

The cash problem

The sharpest constraint is financial. The contractor has invoiced for 51 percent of the work, the threshold for requesting the second instalment of regional funding. The Region has prepared the payment order, but the money has not yet been transferred.

Most municipalities would bridge that gap with a bank advance, but Argentera cannot. It is still in the final phase of its financial-distress procedure and cannot use one. The mayor says the big problem right now is the regional payments, since by law the municipality cannot draw on a cash advance. Argentera is a tiny mountain council, and a delay in Turin can stall a worksite in the valley.

A dispute with the old operator

Even with the work finished, someone has to run the lift. A dispute remains open with the company holding the lift’s management contract. The municipality has hired a lawyer and started proceedings seeking the return of the premises, but it is unresolved. The report does not name the company, though the meter involved in the electrical work was previously registered to Valle Bianca.

For now the administration is considering a provisional management arrangement if an operator can be found once the work ends. No candidate has been announced.

Why it matters

Ciaburro frames the lift as more than a winter amenity. She says it would open the slopes and trails to skiers and to summer hikers, with benefits for the valley’s tourism economy. The same stretch of the Stura valley has also been affected by road disruption linked to the Tenda tunnel works and avalanche risk at the Maddalena pass, which regional papers have flagged as reasons to keep local mountain economies viable (regional documents cite the long-running Tenda tunnel works as a reason to limit road closures).

regione

The lift also had an official safety review behind it. In March 2025 a regional decree dealt with the project for general overhaul to continue operating beyond the lift’s technical life.

What to watch

Four things will decide whether skiers get a chairlift this winter: the final test and approval, the Soprintendenza’s verdict on the wall, the release of regional funds, and whether an operator emerges. Snowfall is a fifth, though nobody in Argentera can influence it.

The mayor says she is satisfied with the quality of the work. The calendar is less forgiving. The target has moved from July to December, and a December test leaves little room for another slip if the season is to be saved.

Sourcing notes: Reporting draws mainly on Neveitalia (5 November) and Targatocn (3 November and 17 June), plus regional documents and earlier local coverage. The mayor’s remarks are paraphrased from those reports. Lift specifications come from a ski-resort database, and the top-station height varies between sources. I couldn’t find an independent source naming the company in the management dispute, so the piece doesn’t name it.