Adelboden's CHF 35.5 Million Cable Car Bet Clears Another Hurdle

Adelboden's CHF 35.5 Million Cable Car Bet Clears Another Hurdle

In this story

Adelboden-Lenk

Resort in Bern, Switzerland

Village height
1,715 m
Top lift
2,194 m
Pistes
83 km
Lifts
21
Nearest airport
Bern Airport (BRN) · 1h 23m
Adelboden-Lenk guide

A long-running plan to replace one of Adelboden's key mountain lifts has cleared a significant procedural milestone, moving a CHF 35.5 million cable car project one step closer to breaking ground — even as its financing and construction timeline remain tight.

What just happened

Follow the story
What's next for Adelboden-Lenk?

Get Adelboden-Lenk news by email.

Follow Adelboden-Lenk

Every landowner affected by the planned route has now agreed to the project, according to Bergbahnen Adelboden AG (BAAG), the resort's mountain railway operator. That unanimous sign-off clears the way for the canton of Bern to approve the development plan and for the project — already filed with the Federal Office of Transport — to go to public review.

The project, named "Direttissima," would replace the existing Sillerenbahn gondola, built in 1990, with a new direct line running from the valley station at Oey up to the Sillerenbühl. Where the current connection takes roughly 25 minutes, largely because it routes through an intermediate stop at Bergläger, the new gondola is designed to make the same journey in about 10 minutes, carrying up to 2,200 people an hour. Separating the new line from the existing Bergläger–Sillerenbühl route is also expected to sharply cut waiting times at that middle station during busy winter periods.

BAAG says it is holding to an ambitious construction timeline that would see the new lift partially open by December 2027, though further procedural and planning steps remain before construction can actually begin.

A financing story as much as a construction one

Getting this far has taken nearly a year of fundraising work. Adelboden's shareholders approved a capital increase for the project back in November 2025, and the Adelboden municipal assembly followed in April 2026, voting to contribute CHF 1 million toward the roughly CHF 5 million in fresh equity BAAG says it needs to unlock already-committed bank financing. The company completed the first tranche of that capital increase in June 2026, worth about CHF 1.4 million, part of a structure that relies heavily on convertible loans — repaid with interest and then converted into shares after one or three years.

As of the most recent count, around CHF 4.9 million in financing has been secured for the new lift, roughly half of it through those convertible loans. A second capital-raising round, expected this autumn, is meant to bring in the municipality's pledged contribution along with other already-committed share subscriptions.

Why Adelboden is willing to spend this much on one lift

The Sillerenbahn sits at the heart of Adelboden-Lenk's largest ski area, Chuenisbärgli-Silleren-Hahnenmoos-Metsch, home to the region's signature World Cup giant slalom and slalom races on the Chuenisbärgli — an annual fixture that draws more than 20,000 spectators to a village of a few thousand residents. BAAG has framed the Direttissima project as more than a lift replacement, arguing that a faster, more direct connection to the Sillerenbühl should encourage visitors to spend longer on the mountain, benefiting skiers, hikers and mountain bikers alike, along with the resort's on-mountain restaurants and events. The company also points to the roughly 350 jobs the mountain railway supports as part of the case for the investment's importance to the wider valley economy.

Part of a broader spending wave in the Swiss Alps

Adelboden's project lands amid a wider capital-spending push across Switzerland's mountain railway sector, as operators replace ageing infrastructure and chase renewed visitor numbers — Swiss mountain railways reported roughly 7% more first-time entries between May and August 2026 than the year before, well above the five-year average, with the Bernese Oberland among the strongest-performing regions. For an industry facing rising energy and maintenance costs on ageing lift networks, faster and more efficient replacements like the Direttissima are increasingly being framed less as luxuries than as competitive necessities.

Whether Adelboden hits its December 2027 target will depend on how smoothly the public review process, remaining permits and a second funding round all come together over the coming months — but for now, the project has one less hurdle standing in its way.